Extension to Factory Waste Irrigation System – Longburn Client: Fonterra Project Manager: James Christensen Job No.: 7556 Site Supervisor: Tony Brill Key features of the work and/or statistics: Location of existing services Staged installation to fit in with farm operations & new factory start-up deadline. Key equipment used: Ditchwitch 6510 Chain Trencher John Deer Tractor & Pipe Trailer Kobelco…

Irrigation – Te Hou

Te Hou Irrigation Client: Waterforce Contract Manager: James Christensen Job No: 7690 Site Supervisor: Tony Brill Key features of the work and/or Statistics Portions of the main line installation were trenched with the Mastenbroek trencher for faster installation. Excavators used on other portions. Key Equipment used: Mastenbroek 2015 Trencher Kobelco SK115 – 11 Tonne Excavator…