RURALIrrigation – Te Hou

Portions of the main line installation were trenched with the Mastenbroek trencher for faster installation. Excavators used on other portions.

Install 2100m of 200mm & 300mm “Z” joint PVC pressure pipe.
Install 500m of power cable complete with mag slab and warning tape protection.
Install 1300m of signal cable.

Key Equipment used:
Mastenbroek 2015 Trencher
Kobelco SK115 – 11 Tonne Excavator
Kobelco SK 70 7 tonne Excavator
John Deere Tractor & Pipe Trailer
Loader

View Other Projects
Client:
Waterforce
Job No:
7690